Install a Metal Driveway Gate

 Home > How to > Fit a Gate > Install a Metal Driveway Gate  

How to Fit a Metal Driveway Gate


Installing new metal driveway gates is usually more straight forward than expected, and most can be carried out by inexperienced DIYers. The main issue that needs to be checked is ensuring the right size gate width/ height has been ordered.

As standard, over 90% of wrought iron driveway gates are installed using the below example:

Fitting set up example for metal driveway gates. Picture showing birds eye view of post/ pillars with gate position.

Basically, the gate is hung between the posts/ pillars and each side will open inwards towards the property.


  • First, a clearance is required between ground level and the bottom edge of gate. We recommend allowing 50mm (or 2") on a level drive although this may need to be increased if the driveway raises.The easiest way to do this is by using a straight edge (ie timber) and a level.
  • Next depends on whether there are posts/ pillars in place or not. If you need to fit posts, see "How to Fit Posts" for more info.

On exisiting pillars or posts: As standard (if no posts are selected on order), you will receive 4 x hinge plates alongwith 4 x adjustable bolts that connects the gate to the plate.

Mounting a hinge plate on a wall ready for a metal driveway gate.

  • Use one side of the gate and position it onto the straight edge. Put the silver threaded bar through the top (pre drilled) hole of gate frame (before this, make sure you remove one of the nuts off the threaded bar.)
  • Connect the bar to the hinge plate and mark the pillar/ post where the hinge plate needs to be mounted.

Repeat this process for the bottom hinge plate but using a spirit level to ensure the gate is plumb then move on to opposite side. This stage needs to be accurate so spend time to get it right!

  • Using a hammer drill, drill the holes. Insert the wall plugs until they are flush with the surface. Fix the 4 hinge plates to the posts/ pillars.
  • Connect the four threaded bars to the gate frame and hang. Using the nuts, adjust untill the centre opening gap is approx 10mm. By adjusting either the top or bottom you can get the gates to be level with each other.
  • Once complete, put the gates into the closed position and release the two drop bolts (pre attached to gate) and mark the ground. Then, fully open the gates and mark where the drop bolts hit the ground. When happy with the position, drill the four holes. This will allow the gate to be secured in place if open or closed.
Handy Tip: If you find when closing the gates the centre of the two is not flush from top to bottom (which can be caused by the posts being slightly out of level, or a slight twist in the frame) then you can force the gate to twist t untill it becomes right. Using two people one holds a certain area whilst the other person can pull or push it. Straps can also be used to achieve the same result (always ensuring it is safe to do so and the posts are firmly fixed into the ground)

Tools Required:

  • Spirit Level
  • Hammer Drill
  • Hammer
  • Spanner
  • Scewdriver
  • Pencil
  • Tape Measure
Prefer Gates and Fences UK to carry out a full gate installation for you? See here.